Promenade Rework

Sammut Marine started the precast process at the contractor's yard. Works started by surveying area and constructing 28 different precast panels. In the meantime, another team was responsible for the demolition of the existing precast panels. For this section of this project, Sammut Marine followed by carefully works at Balluta Bay breaking half of the ring beam on the seaward side using hand held tools while avoiding damage to the existing arches. Once the above works were completed, precast panels were brought to site and hoisted to their location. Further onsite reinforcement was installed and area was casted in-si.